Sunrise Ridge Update Wednesday December 7

It has been a cold week at the construction site at Sunrise Ridge.  Even in the cold, the work has continued.  This week the final landscape grading was completed on 4008 and 4010 Rock Creek.  The work on landscape will continue as weather permits.  Before the ground freezes the irrigation system and edging will be installed.  The electrical work on both 4008 and 4010 is all completed.  Roofing work continued and is nearly complete.   

Next week the gas service will be installed and rough inspections shall be completed. 

The digging of 4014 and 4016 has been scheduled.  The holes for those two homes have been scheduled for 12/26.  The excitement is about to begin.