Happy almost Chinese New Year!  We have had a week of good weather and things are moving along.  This week they will be finishing the fire sprinklers in 4010 and 4008 Rock Creek.  Drywall will be hung on Thursday or Friday this week.  The exterior stone work will also be started this today, these two homes are getting closer to completion.  The next hole for 4014 and 4016 Rock Creek will be dug in the next few days.  We are excited to be starting on the next two homes.  Give us a call today because now is your chance to make one yours!