Sunrise Ridge Update Monday May 14

Rain…rain…go away.  We have certainly had some wet days out at Sunrise Ridge over the last week.  We have the holes dug for both homes on Lot 4.  Now once the hole is dug we will do additional soils samples and analysis.  This is part of the “open hole” inspection.  We will have some idle time once the hole is dug to completed these tasks.  It will look like nothing is happening…but there will be things going on behind the scenes.  Once the soil analysis is back we will be able to get going on the foundation and work will start in the hole. Now is the time if you want to call a Sunrise Ridge home yours there is one lot left in this release, and it may be our best lot. If you are interested call or text Lestel @ 970-310-8379 to learn more or you can fill out the Request Information sheet. To get weekly updates like and follow us on Facebook.