Happy Wednesday.  Yesterday we had some grading to prepare the lots as well as follow up surveying.  Survey crew has been out and about finalizing to make sure that each house is exactly where it needs to be before foundations are poured.  You can see in the pictures one of their pink spray paint lines, those lines are all over the place out at the construction site.  Some foundation equipment is now on site, and the foundation crew starts forming tomorrow on Lot #4.  Lot #3 should be starting to be poured at some point mid to late next week.  Work will begin to move from behind the scenes work to production that you can actually see.  We are all looking forward to that!