Sunrise Ridge Update Tuesday May 14

Wow what a difference a week makes. Sheeting is almost complete on 5218 Sunglow (Lot 4B) and the framers have already started sheeting the other side 5220 Sunglow (Lot 4A). Framing has been progressing swimmingly on both homes. Once this framing phase is complete HVAC will be installed before other work can move forward. Additionally, window delivery occurred this morning for basement windows.