Sunrise Ridge Update Friday September 6th

We have progress going on at Sunrise Ridge. The stucco guys have been working
hard this week and last week on the exteriors of 5218 and 5220 Sunglow Ct. We
have four layers that make up the exterior finish of the houses out at Sunrise
Ridge. The first layer is the water proof layer, next is netting that looks like
chicken wire and the last two are actually troweled on. We have the first three
layers on. The last will be the most exciting because it will be the color coat. I
never know what color the house will be until that is applied.
Inside we have our electrical completed on 5218 Sunglow Court and we have a
live electrical panel. I say that it is complete…but we still need fixtures and
switches. However the rough electrical is done. Work has also been occurring on
our sprinkler system. Each home at Sunrise Ridge has a sprinkler system in case of
fire. That is a City of Fort Collins code requirement for attached dwellings. This
system is quite elaborate and requires much time to install. But our neighbors are
safer if there was a fire. Next post should be pictures of stucco complete and we will know the house color of 5218 Sunglow Ct. Until then, enjoy the last heat of summer.