Sunrise Ridge Update Friday November 29

Progress continues at 5218 Sunglow. The framing has been completed in the basement for the two bedrooms and the bath that were requested by the customer. We also have had the basement windows added. There was some dirt flying around the properties at 5218 and 5220. It is much easier to access the homes for the tradesmen. We are not yet ready for the concrete for patios or driveways but it is much easier to get around. General site clean-up occurred and we are looking nice and clean again.

The snow slowed progress, as did the Thanksgiving. We are going to hit it hard the first week of December! We are thankful for our past and present customers. Wishing you a blessed Thanksgiving and holiday season!